Status Update on Caltrain’s CBOSS PTC Project
By Caltrain Modernization Staff As Caltrain continues to upgrade its communications and signaling system, the rail agency would like to share the current status of the CBOSS PTC program. The […]
The Official Blog of Caltrain, SamTrans and TA.
By Caltrain Modernization Staff As Caltrain continues to upgrade its communications and signaling system, the rail agency would like to share the current status of the CBOSS PTC program. The […]
By Caltrain Modernization Staff
As Caltrain continues to upgrade its communications and signaling system, the rail agency would like to share the current status of the CBOSS PTC program. The Caltrain Modernization Program has three critical elements: the installation of an advanced signal system and the installation of electrical infrastructure along the corridor along with the purchase of new vehicles to operate the electric service.
CBOSS PTC will play a critical role in improving the efficiency and safety of rail operations, post-electrification, and it also fulfills the federal government mandate to install positive train control to improve the safety of rail operations on corridors where passenger and freight operations share the tracks.
Over the last several years, staff has been providing the Joint Powers Board, which oversees Caltrain, with regular updates about the groundbreaking new technology that will form the basis for the CBOSS PTC system. But as with the development of any new technology, unforeseen challenges and issues beyond our control can cause delays in implementation.
In April, Caltrain requested that the American Public Transportation Association’s Peer Review Panel take a closer look at some of the challenges that the CBOSS PTC Project is facing and make recommendations on how to strengthen the project delivery efforts. Caltrain received the final report in July and has been working on implementing many of the recommendations it provided.
Below are some Frequently Asked Questions about the CBOSS PTC Project, in addition to a link, CLICK HERE, to the full APTA Peer Review Report.
Caltrain CBOSS PTC APTA Peer Review Report Background
The Communications Based Overlay Signal System (CBOSS) Positive Train Control (PTC) system is an advanced signal system that will monitor and control train movements, providing significant safety improvements, increased reliability and operating performance, and improved capacity and service.
The project also fulfills a federal mandate that requires implementation of a Positive Train Control (PTC) system on all commuter corridors. PTC is intended to prevent train-to-train collisions, over-speed derailments, and movement into established work zones or through a misaligned switch.
In response to a fatal train collision in September 2008 on the Metrolink System, Congress passed the Rail Safety Improvement Act (RSIA) of 2008, which updated the Code of Federal Regulations (CFR) to require PTC to be installed along every passenger rail corridor prior to December 31, 2015. In 2015, Congress passed a PTC extension which mandates implementation of PTC by December 2018.
For Caltrain, the core safety enhancements provided by PTC include the prevention of:
Caltrain is one of a handful of railroad operators nationwide that has completed installation activities and has commenced testing of the system.
APTA’s Peer Review Program is designed to assist transportation organizations in addressing public transportation-related needs and issues through subject matter experts within the public transportation industry. Through the coordination by APTA and the support of their respective own organizations, the subject matter experts convene at the requesting public transportation organization and conduct an intensive review of the issues to be addressed. Peer Review participation is conducted by mutual consensus and through industry acknowledgement that this service is an extremely valuable resource to strengthening and enhancing public transportation functions and effectiveness.
In April 2016, Caltrain requested the APTA Peer Review to have a third party take a closer look at some of the challenge areas that the CBOSS PTC Project was facing and make recommendations on how to strengthen the project delivery efforts.
In May 2016, the Peer Review team was formed with experts from around the country that are familiar with the PTC federal mandate. In June 2016, the APTA Peer Review team spent several days looking at the project and meeting with key personnel from Caltrain staff, the contractor (PTG) and railroad support staff (TASI). Caltrain received the final report in July 2016.
Caltrain staff have mentioned that the APTA Peer Review was in process at previous Board meetings and there will be an update on the Peer Review Report at the August 7, 2016 Board meeting.
Caltrain has already taken several steps to implement many of the recommendations. Key elements for Caltrain include:
On a regular basis, Caltrain staff reports to the Peninsula Corridor Joint Powers Board (consisting of representatives from San Francisco, San Mateo and Santa Clara counties) on the status of the CBOSS PTC project. A link to the board website can be viewed here: http://www.caltrain.com/about/bod.html
Caltrain also has a project management oversight committee that consists of members of the Caltrain Executive Team that meets on a monthly basis.
Caltrain has a weekly call between the JPB Executive Director and the PTG CEO. The Caltrain Chief of Rail also has a weekly call with the PTG Vice President. Additional monthly meetings are held between Caltrain project management and their counterparts at PTG and their subcontractors.
For the last three years, CBOSS PTC staff has provided monthly briefings on the CBOSS PTC project to staff from the parties that signed the 9-party MOU for the Early Investment Projects (that includes CBOSS PTC).
Finally, as part of a recent agreement with the 7-parties to the Early Investment Supplemental Funding MOU, there is a Funding Partners Oversight Protocol for the CalMod Program (including CBOSS PTC). The protocol outlines the open door policy with the funding partners and encourages their participation. A copy of the protocol can be found by clicking the link here.
CBOSS PTC is a key element of the CalMod Program, which includes electrification of the corridor and replacement of the system’s diesel trains with high-performance electric trains. Of the overall CalMod Program, the CBOSS PTC project accounts for $231 million of the total cost.
The project is partially funded through the 2012 early investment 9-party MOU. The 2016 7-party Supplemental MOU only funds the Peninsula Corridor Electrification Project.
Yes. The CBOSS PTC Project has taken longer than expected. Caltrain is currently in commercial negotiations with the contractor. Caltrain asked that the contractor to establish a new schedule that reflects the additional time needed by the contractor and take responsibility for the current delays for the project.
The Caltrain Board has approved $14.3 million in their FY17 budget. However, the exact amount will be determined through the commercial negotiation.